JZC350 Concrete Mixer Specifications: Reading the Real Numbers

The JZC350 is a 350-litre discharge, tilting-drum concrete mixer typically rated at 10–14 m³/h with a 5.5 kW motor, a 560-litre charging volume, 14 rpm drum speed and a 60 mm maximum aggregate size. Those figures describe capacity per batch, not output per shift. Real output depends on how fast you can feed the drum, and that is where most buyers get surprised.

Why two suppliers quote different JZC350 numbers

Search the same model across suppliers and the specification tables disagree on nearly everything: 5.5 kW or 7.5 kW, 800 kg or 1,000 kg, 10 m³/h or 14 m³/h, 350 L or 400 L. None of them are necessarily lying. The JZC350 is a general arrangement, not a controlled standard, and different factories build it with different drum thickness, frame steel, tyre size, motor brand and discharge mechanism.

That matters because the model number tells you the drum class, not the build quality. Two machines both called JZC350 can differ by 200 kg of steel and by several years of service life. Treat every published figure as a starting point to verify, not a specification to trust.

The capacity figures and what each one controls

Parameter Commonly published value What it actually controls
Charging volume 560 L How much raw material fits per batch before spillage
Discharging volume 350 L Mixed concrete yielded per batch, roughly 0.35 m³
Drum speed 14 rpm Mixing time and segregation behaviour
Motor power 5.5 kW (some builds 7.5 kW) Starting torque under a full drum and thicker mixes
Maximum aggregate 60 mm Whether local stone is usable without screening
Productivity (nameplate) 10–14 m³/h Throughput assuming uninterrupted feeding
Net weight 800–1,000 kg Towing vehicle class and site transport

The 560/350 split is a fill ratio, not a trick. A drum loaded to the charging volume leaves room for the mix to tumble instead of packing solid against the blades. Overfilling to gain yield per batch costs mixing quality and motor load, and it is the most common operator error on this size of machine.

Where the 10–14 m³/h figure comes from

Do the arithmetic and the nameplate stops being mysterious. At 0.35 m³ per batch, 10 m³/h requires about 29 batches per hour, or roughly 124 seconds per cycle. 14 m³/h requires about 40 batches per hour, or 90 seconds per cycle. Both assume the drum is never waiting for material.

A 90-second cycle is achievable with a mechanical hopper feed and dry, free-flowing aggregate. It is not achievable when two labourers shovel sand from a ground pile, when the skip hopper has to be manually filled, or when the mix needs longer to reach uniformity. Most sites running a JZC350 by hand settle somewhere between 5 and 9 m³/h, and that is a labour constraint rather than a machine fault.

If the pour needs a dependable 12 m³/h, the honest answer is a larger drum with a mechanical charging system, or a batching arrangement — not a JZC350 pushed harder.

Power supply: the check that stops installations

A 5.5 kW motor on 380 V three-phase draws roughly 11–14 A at full load, and starting current is several times that. On a site with a small generator or a long temporary cable run, voltage drop causes the motor to stall under a full drum — usually at the worst moment, with a batch half mixed.

Three things to confirm before delivery: the supply is genuine three-phase rather than a single-phase converter, the cable cross-section matches the run length, and the generator rating accounts for starting current rather than running current. If the site has no three-phase supply at all, a diesel-driven mixer is the correct answer and no amount of wiring will fix it.

What the tilting drum does well, and what it does not

The JZC series is a self-falling, tilting-drum design: blades lift and drop the mix, and the whole drum tilts to discharge. That suits plastic and semi-dry mixes at moderate slump. It handles them with low power demand and simple maintenance.

It does not suit three categories well. Very stiff or zero-slump mixes do not tumble and tend to ball up. Fibre-reinforced mixes wrap around the blades. And high-output continuous work exposes the tilting mechanism and the discharge chute to wear that a fixed-drum or twin-shaft machine absorbs more gracefully.

For structural concrete at scale, a twin-shaft or pan mixer produces a more uniform mix in a shorter cycle. For small pours, repairs and secondary structure, the drum mixer remains the cheaper and more mobile option.

Maintenance points that decide service life

Four items account for most premature failures on this machine class.

  • Drum blade clearance. Blades wear and the gap to the drum shell grows, leaving unmixed material at the bottom. Check the gap periodically and adjust or replace before mixing quality drops.
  • Tilting mechanism and locking. The pivot and the locking pin take the full load of a wet drum. Grease them on a fixed schedule, not when they squeal.
  • Water tank and dosing valve. Scale and grit block the valve, and operators compensate by guessing. A blocked valve silently changes the water-cement ratio on every batch.
  • Tyres and towing frame. Towing at road speed with a loaded drum punishes the frame. Check welds and tyre pressure before any move between sites.

Cleaning is the fifth, and it is behavioural. A drum left with concrete overnight needs a hammer and chisel in the morning, and the impact damages the shell. Wash out at the end of every pour while the mix is still green.

Choosing between a JZC350 and the next size up

The 350 L class suits pours under about 15 m³ a day, repair and secondary-structure work, and sites where a single operator handles batching. Move up a class when any of these is true: pours regularly exceed 20 m³ a day, the mix design needs mechanical charging to hit schedule, or the site runs two placing crews from one machine.

If the concrete then has to travel horizontally or rise above a chute, the mixer is only half the decision. Our comparison of self-loading mixers and truck mixers covers batching logistics, and the trailer, mixer and line pump comparison covers how concrete reaches the formwork once it leaves the drum.

Frequently asked questions

How many bags of cement does a JZC350 batch take?

It depends entirely on the mix design, because the drum is rated by volume rather than by cement content. Work from the yield: one batch produces about 0.35 m³ of mixed concrete, so multiply your mix design’s cement content per m³ by 0.35. Confirm the figure against your own trial batch rather than a generic table.

Can a JZC350 run on single-phase power?

Not in its standard three-phase build. Single-phase conversions exist for small drum mixers, but they lose torque and stall under a full load. If only single-phase power is available, choose a diesel-driven unit or a smaller single-phase machine matched to the actual batch size.

What size aggregate can a JZC350 mix?

The commonly published limit is 60 mm, which suits most local crushed stone without screening. Oversized or elongated stone jams between blade and shell, and the resulting load spike is a frequent cause of motor and coupling failure.

Is JZC350 the same as JZC400?

No. The number refers to discharge volume in litres, so a JZC400 yields roughly 0.4 m³ per batch from a larger drum and typically needs more power and a heavier towing vehicle. Confirm drum dimensions, motor rating and weight per model, since build details vary between factories.

Next step: send us your daily pour volume, mix design and available power supply, and we will tell you whether the 350 L class fits or whether the pour needs a larger drum or a pump on the discharge side. See the mixer and pump range for the matching options.