A concrete pump rated at 40 m³/h will place 24–30 m³/h on a normal site — 60 to 75% of the nameplate. The gap is not a defect. Rated output is a hydraulic displacement figure measured with water at maximum stroke rate; actual output is that figure after volumetric losses, mix resistance, pipeline friction and the concrete truck cycle have taken their share.
If you size a pour on the nameplate number, you will order too few trucks, run the pump at maximum pressure, and finish the day short. Size on 65% of rated output and the schedule holds.
First, how the nameplate number is produced
Every piston pump’s rated output comes from one multiplication:
Q = piston area × stroke length × strokes per minute × 60
A typical 40 m³/h trailer pump runs 180 mm pistons with a 1,400 mm stroke. Piston area 0.0254 m², so each stroke displaces 0.0356 m³. At 19 strokes per minute that is 40.6 m³/h — which is where the catalogue number comes from.
Three things are already assumed inside that number: full cylinder fill on every stroke, water-like flow resistance, and a continuous supply of concrete at the hopper. None of the three survives first contact with a real pour.
The loss chain, stage by stage
| Stage | What happens | Typical efficiency | Effect on a 40 m³/h rating |
|---|---|---|---|
| Volumetric efficiency | Valve slip, piston seal leakage, air entrainment | 88–94% | 40 → 36.5 |
| Cylinder fill ratio | Stiff mix or fast stroking cannot fill the cylinder | 85–93% | 36.5 → 32.5 |
| Pipeline resistance | Friction in pipe, elbows and vertical riser caps pressure, forcing a lower stroke rate | 90–97% | 32.5 → 30 |
| Supply continuity | Pump waits for the next agitator truck | 70–85% | 30 → 24 |
| Operator / finish work | Hose moves, placing stops, cleaning between sections | 92–97% | 24 → 23 |
Multiply the stack and you land between 0.55 and 0.75. Everything above that is a good day, not a normal day.
The two line items buyers never budget for are the last two. A pump that is mechanically perfect will still deliver 24 m³/h if the batch plant sends one truck every twelve minutes.
Worked example: the 40 m³/h pump
- Rated output: 40 m³/h
- Volumetric efficiency 92% → 36.8 m³/h
- Cylinder fill 88% on a 140 mm slump mix → 32.4 m³/h
- Pipeline loss 94% with 90 m of 125 mm pipe and four elbows → 30.5 m³/h
- Truck cycle 75% (one 6 m³ truck every 8 minutes against a 30 m³/h demand) → 22.9 m³/h
Placed output: about 23 m³/h. For a 200 m³ slab that is 8.7 pumping hours, not 5. Quote the client 8–9 hours and add a cleaning window.
A useful planning rule: order equipment at 1.4× the required hourly demand. Need 30 m³/h placed? Specify a 42 m³/h machine, not a 30.
How to measure your own actual output in 15 minutes
Do this once, before you promise a schedule.
- Truck-batch method (most reliable). Note the batch volume of each agitator truck, note the time the first concrete enters the hopper and the time the last truck is empty, subtract idle waiting. Placed volume ÷ pumping time = actual output.
- Stroke-timing method. Time 20 strokes with a stopwatch, divide by 20 for seconds per stroke, then multiply by the volume per stroke from the formula above. This gives machine output, not placed output — the difference between the two is your supply and pipeline loss.
- Hopper drawdown. With a known mix and a steady stroke rate, mark the hopper and time how long a fixed drop takes. Rough, but it catches a worn pump fast.
Record the three numbers — machine output, placed output, and waiting time — and you can attribute the loss to the machine, the mix or the logistics instead of arguing about it.
When actual output falls below 60%, check these in order
- Wear ring and cutting ring gap. On an S-valve pump, a gap above roughly 0.5 mm lets grout slip past the valve on every stroke. Symptom: pressure looks normal, output drops, mix stiffens in the line. See S-valve wear symptoms.
- Piston cups and guide rings. Torn cups pass material behind the piston — output falls and the hydraulic oil heats up.
- Mix workability. Below 120 mm slump, fill ratio collapses. Target 140–180 mm slump for pumped mixes, with sand ratio around 40–45% and maximum aggregate within one third of the pipe diameter.
- Aggregate size against pipe diameter. 40 mm aggregate in a 100 mm line bridges at the elbow. The industry rule is pipe diameter ≥ 3× maximum aggregate size.
- Pipe layout. Every 90° elbow equals several metres of straight pipe. Ten elbows on a 60 m run behave like 100 m of straight line.
- Hydraulic settings. Relief pressure set low, or a tired main pump, caps stroke rate under load. Check the pressure gauge at the pump while stroking.
- Hydraulic oil temperature. Above roughly 70 °C, oil thins and volumetric efficiency falls; the machine sounds normal while losing 10%.
If the pump has simply stopped building pressure, work through concrete pump not pumping troubleshooting instead — that is a different failure mode.
What to tell the buyer before they sign
- Ask every supplier for output at a stated pressure and pipe size, not a bare m³/h.
- Ask for the stroke rate and piston diameter — you can then verify the rating yourself in thirty seconds.
- Expect 60–70% of rating in the pour plan and in the contract schedule, and budget the machine against the delivered cost per cubic metre rather than the sticker price.
- If output is the deciding factor — high-rise, long horizontal runs, dense mix — the sizing method matters more than the catalogue number, and on tall buildings the pressure calculation decides the machine class.
FAQ
Is rated output measured with concrete?
No. It is normally measured with water or a thin slurry at maximum stroke rate — the best case the hydraulics can produce. Treat it as a ceiling, not a promise.
Why do two pumps with the same rated output differ on site?
Valve design, hydraulic pressure reserve, engine power under load, and how the machine behaves when the mix stiffens. Two identical numbers can differ by 20% in placed output.
Will a larger pipe increase output?
It reduces friction and pressure loss, which allows a higher stroke rate at the same pressure — but it does not change displacement. Larger pipe helps long runs; it will not fix a worn valve.
Can a 40 m³/h pump ever hit 40 m³/h?
Only with continuous truck supply, a wet mix, a short straight line and a new wear plate. That combination is a test bay, not a construction site.