Size a concrete pump from the pour, not from the brochure. Work out the cubic metres per hour you actually need, add the pressure required to lift the mix, then check pipe diameter against your largest stone. For most low-rise and mid-rise work a 40–60 m³/h trailer pump covers the job, and the pressure rating only becomes the deciding number above roughly 100 m of vertical lift.

The three questions buyers send us are always the same shape: how tall, how far, and how many cubic metres per shift. Those three answers narrow the choice to a model class before price, brand or origin ever enters the conversation. What follows is the arithmetic we use to answer them, so you can run it yourself.

Four numbers decide the size, and three of them come from your site

Every pump enquiry reduces to a required output, a required pressure, a pipe diameter and an aggregate size. Get those four right and the model follows. Get them wrong and you either pay for capacity you never use or discover in the middle of a slab pour that the machine cannot push the mix to the top floor.

The mistake is to start from a machine — a 40 m³/h unit because a neighbour has one, or a 16 MPa unit because tall buildings supposedly need them. Start from the pour and most of the confusion disappears.

Step one: convert your pour schedule into m³/h

Take the largest single pour you will place, divide by the hours you are willing to keep the crew and the mixer trucks on site, and you have a working output figure. A 90 m³ footing placed in four hours needs 22.5 m³/h at the nozzle.

That is not the number to match against a nameplate. Rated output is measured under favourable conditions: a steady supply of pumpable mix, a short line, a clean pipe and an operator who is not stopping to reposition. In real work, plan on 60–75% of the rated figure. A pump rated at 40 m³/h delivers somewhere around 24–30 m³/h through a normal site line, which is why a 40-series machine is a common choice for pours in the 20–30 m³/h band and a poor choice for one that needs 35.

Two things cut that figure further and should be priced in. Long horizontal runs reduce output before they reduce pressure, because every metre of pipe adds friction and every bend adds a small stop-and-restart. And a mixer pump that batches on site is limited by its own batching cycle, not by its pumping capability.

Step two: work out the pressure to lift the mix

Vertical lift is the easy part, because it is physics rather than opinion. Concrete at about 2,400 kg/m³ develops roughly 0.024 MPa of hydrostatic head per metre of height. Sixty metres of rise therefore costs about 1.4 MPa before friction is counted.

Pipe friction is where the estimating gets soft. Published friction tables for pumped concrete put losses somewhere between 0.008 and 0.02 MPa per 10 m of straight 125 mm line, depending on slump, cement content and pumping rate. Use the upper end for stiff or low-cement mixes and the lower end for well-graded, higher-slump concrete. Each 90° bend is usually treated as 3–5 m of equivalent straight pipe.

A worked case for a 60 m rise, 120 m of horizontal line and eight bends:

Item Assumption Pressure cost
Vertical lift 60 m × 0.024 MPa/m 1.44 MPa
Horizontal pipe 120 m at 0.012 MPa/10 m 0.14 MPa
Bends 8 × 4 m equivalent at 0.012 MPa/10 m 0.04 MPa
Working margin 20% for cold mix, slow pumping, restart losses 0.32 MPa
Required pump pressure Total at the outlet 1.94 MPa

The result is the point most buyers miss. An 11 MPa machine has more than five times the pressure this job needs. Pressure ratings look dramatic on a specification sheet, but below about 100 m of rise they are rarely the constraint; output, pipe size and mix design are. Buying 16 MPa for a six-storey building solves a problem the site does not have, while an undersized hopper or an oversized aggregate quietly stops the pour.

Step three: match pipe diameter to your aggregate

Pipe diameter sets the largest stone the line will pass. The long-standing rule of thumb is that maximum aggregate should not exceed about one third of the pipe’s internal diameter, tightened to one quarter for harsh, angular or low-fines mixes. On a 125 mm line that means 40 mm stone at the outer limit; on a 100 mm line, 30 mm is already ambitious.

This is the check that decides whether you buy a pump or a screen. If the local quarry delivers 40 mm crushed stone and the site wants to use it, the line has to be 125 mm or larger, the bends have to be long-radius, and the mix needs enough fines to carry the stone. Squeezing 40 mm aggregate through a 100 mm line works until it does not, and when it blocks at 40 m of height the recovery cost is a day of the programme.

Smaller lines are not automatically worse. Grout and fine-mix work runs happily through 50–65 mm hose, and secondary-structure pours benefit from the flexibility. The rule is simply that pipe, stone and mix have to be chosen together.

Step four: match the arithmetic to a model class

With output, pressure, pipe and aggregate fixed, the shortlist is usually two or three machines. The table below maps the trailer and mixer-pump classes we build onto the jobs they suit. Rated figures come from the datasheets; confirm the output figure for the exact build before you order, because models with similar numbers can differ in hopper volume, valve type and hydraulic layout.

Model Pressure / power Best fit What to check first
HBTS40-11-45 11 MPa / 45 kW Low-rise structures, secondary structure, residential floors, pours around 20–30 m³/h Whether site power can carry the motor plus the rest of the site load
HBTS60-13-90 13 MPa / 90 kW Mid-rise buildings, longer horizontal runs, higher sustained output Three-phase capacity and cable size at the actual run length
HBTS80-16-110 16 MPa / 110 kW Tall cores, long lines, large single pours Line diameter and mix design, not just the pump
JBT50 mixer pump 50 m³/h, 10 MPa, Kawasaki hydraulic pump Sites with no ready-mix supply; batching and pumping in one machine Batching cycle and material storage, which set the real output
40 m³/h diesel trailer Vertical 60 m / horizontal 180 m, Weichai engine Sites without grid power, remote work, rental fleets Fuel logistics and the duty cycle you expect in a shift

Two of those rows deserve a note. The 40 m³/h diesel unit is quoted at 60 m vertical and 180 m horizontal because that is the envelope we publish; a site that needs both at once should treat the numbers as separate limits rather than adding them. And the JBT50 mixes and pumps through one machine, so its practical output depends on how fast you can feed cement, sand and stone — the 50 m³/h figure describes the pumping side.

Where sizing usually goes wrong

Three patterns account for most of the mismatches we see.

Buying pressure instead of output. A tall building needs pressure, but a six-storey building with a 250 m horizontal run usually needs volume through the line more than it needs megapascals. Check the friction term before assuming height is the problem.

Sizing to the average pour. Machines are bought for the hardest day, not the typical one. If one slab a month needs 40 m³/h and everything else needs 15, the decision is whether to rent for that slab or accept a slower day.

Ignoring the mix. A pump that meets the output and pressure requirement can still fail on a mix with too little fines, too much stone or a slump the machine cannot handle. Send the mix design with the enquiry, not after the machine arrives.

What to put in an enquiry so the answer is right the first time

Five lines are enough: maximum single pour in cubic metres, hours available for it, vertical rise, total horizontal run including bends, and the largest aggregate your supplier delivers. Add the power supply — three-phase, single-phase or none — and the answer stops being a guess.

Every machine we ship runs a five-hour continuous test before it leaves, and the buyer receives an operation video of their own unit. That does not replace the sizing calculation, but it does mean the machine you receive has already pumped for a working shift.

Frequently asked questions

What size concrete pump do I need for a three-storey house?

A 40 m³/h class trailer pump is normally enough, provided the line stays at 125 mm and the aggregate is 30 mm or smaller. The vertical lift is about 9 m, so pressure is not the constraint; access, line length and the number of bends usually are.

Can a 40 m³/h pump place 100 m³ in a day?

Yes, and it has margin. At 60–75% of rated output the machine delivers roughly 24–30 m³/h, so 100 m³ is three to four hours of pumping. The real question is whether trucks, labour and finishing can keep up with that rate.

Is 11 MPa enough to pump up 60 m?

Yes. Sixty metres of lift costs about 1.4 MPa, and a normal site line adds well under 0.5 MPa. The limits you are more likely to hit are pipe diameter against aggregate size, and output against the pour schedule. Confirm the figures against your own line layout rather than a rule of thumb.

Do I need a bigger pump for a long horizontal run or a tall building?

They load the machine differently. Height costs pressure steadily; horizontal distance costs both friction and output, and it multiplies with every bend. A 200 m horizontal run at ground level can demand more from the pump than a 60 m rise, which is why the layout drawing matters more than the building height.

Next step: send the five numbers above and we will return a model recommendation with the pressure and pipe size worked out for your layout. See the trailer and mixer pump range, or read the trailer, mixer and line pump comparison if you are still deciding which machine type suits the site.